Porsche Dealership | Located in Florida
Challenge
Project Overview:
AEODC supported the development of a new Porsche dealership in North Miami, FL. The facility includes a two-level showroom (38,612 SF), a six-level garage (281,093 SF), and a service drive area (79,130 SF).
Challenges:
Complex integration of showroom, garage, and service areas.
Detailed coordination across disciplines to prevent on-site issues.
Strategies:
Applied LOD 400 standards for detailed and accurate modeling.
Conducted thorough clash analysis and proactive issue resolution.
Maintained close collaboration with stakeholders to streamline design and execution.
Project Overview:
AEODC supported the development of a new Porsche dealership in North Miami, FL. The facility includes a two-level showroom (38,612 SF), a six-level garage (281,093 SF), and a service drive area (79,130 SF).
Challenges:
Complex integration of showroom, garage, and service areas.
Detailed coordination across disciplines to prevent on-site issues.
Strategies:
Applied LOD 400 standards for detailed and accurate modeling.
Conducted thorough clash analysis and proactive issue resolution.
Maintained close collaboration with stakeholders to streamline design and execution.
Solution
Services Provided:
Model Enhancement: Upgraded architectural, structural, and MEP Revit models from LOD 300 to LOD 400.
Clash Detection & Coordination: Utilized Navisworks for clash detection and led coordination meetings to resolve conflicts pre-construction.
Services Provided:
Model Enhancement: Upgraded architectural, structural, and MEP Revit models from LOD 300 to LOD 400.
Clash Detection & Coordination: Utilized Navisworks for clash detection and led coordination meetings to resolve conflicts pre-construction.
Results
Outcome:
AEODC’s expertise in model enhancement and clash coordination played a critical role in ensuring the project's success. By upgrading all Revit models to LOD 400 and conducting extensive clash detection using Navisworks, AEODC helped eliminate design conflicts before construction began. The team's proactive approach to coordination and communication reduced rework, minimized delays, and supported an efficient construction process. As a result, the Porsche dealership project advanced smoothly through design and into execution, with improved accuracy, cost control, and project timeline adherence.
Outcome:
AEODC’s expertise in model enhancement and clash coordination played a critical role in ensuring the project's success. By upgrading all Revit models to LOD 400 and conducting extensive clash detection using Navisworks, AEODC helped eliminate design conflicts before construction began. The team's proactive approach to coordination and communication reduced rework, minimized delays, and supported an efficient construction process. As a result, the Porsche dealership project advanced smoothly through design and into execution, with improved accuracy, cost control, and project timeline adherence.